Six stages separate a delivered isolator from an accepted installation, and the stage that gets skipped is the first one. Without a floor baseline taken before the platform arrives, nobody can prove the installation worked, and a specification written as "VC-D or better" becomes an argument at handover. The order is fixed: survey, positioning, fixing, leveling, pneumatic setup, acceptance. Each stage produces a number the next one depends on.
Stage 1: site survey and pre-installation checklist
|
Check |
Instrument |
Pass condition |
If it fails |
|
Floor flatness |
Frame level, 0.02 mm/m |
0.5 mm over the footprint, 0.2 mm for air |
Grout or add a plinth |
|
Point load capacity |
Slab drawing, core sample |
1.5 times the working load |
Spread load with a steel beam |
|
Vibration baseline |
Three-axis vibrometer, 1/3 octave |
Below the VC band for the tool |
Change isolator type before ordering |
|
Acoustic background |
Sound level meter |
Below the tool maker's limit |
Move or enclose the compressor |
Record the baseline as a 1/3 octave spectrum: a floor reading 20 µm/s overall can still fail at 8 Hz, and that band is where the isolator works.
Stage 2: positioning, where the support points go
Support points belong under the mass, not the frame corners. Four points suit a centred load with a length-to-width ratio below 1.5; six or more are needed above a ratio of 2, or when the load is offset beyond 20 percent.
|
Layout question |
Rule |
Check on site |
If it is wrong |
|
How many points |
4 below ratio 1.5, 6 above 2 |
Measure the frame drawing |
Corner overload |
|
Position |
Symmetric, equal moment arms |
Plumb line from lifting points |
One isolator at 150 percent |
|
Offset tolerance |
20 percent before adding points |
Weigh each corner |
Level drifts over weeks |
An off-centre microscope column is the usual failure: the rear isolators unload and the table tilts until the valve runs out of stroke.
Stage 3: fixing, matching the anchor to the slab
Four options cover most sites: expansion anchors in sound concrete, chemical anchors in cracked or vibrating concrete, an embedded plate welded to a cast-in base, and through-slab bolting below 120 mm. Torque goes on in diagonals, two or three passes: M10 at 35 to 45 N·m, M12 at 60 to 75 N·m, M16 at 150 to 190 N·m for grade 8.8 dry threads.
Stage 4: leveling, coarse to fine in a fixed order
Leveling runs from mechanical to pneumatic to electronic, since a valve cannot correct a floor that is out by 8 mm.
|
Step |
Action |
Instrument |
Target |
Why this order |
|
1 |
Mechanical coarse level |
Frame level, 0.02 mm/m |
1 mm over the footprint |
Keeps the valve inside its stroke |
|
2 |
Release transport locks |
Visual, per isolator |
Lock fully clear |
A locked isolator measures as rigid |
|
3 |
Admit air, auto-level |
0.4 to 0.6 MPa supply |
Table floats, valve stable |
The valve needs pressure to null |
|
4 |
Fine level |
Electronic level, 0.01 mm/m |
0.1 mm repeatability |
Resolves what a bubble cannot |
|
5 |
Rest and re-check |
Same instruments |
Unchanged after 24 hours |
Catches creep and leaks |
Step 2 produces most support calls: a table with the lock engaged feels solid, levels badly and shows no isolation.
Stage 5: pneumatic setup, the air side of the installation
Air quality is a specification, not a preference: 0.4 to 0.6 MPa at the regulator, dew point −20 °C or lower, oil content 0.1 mg/m³ or less, three-stage filtration for water, oil and dust. Pipework must not bridge the isolator, because a rigid run from floor to table bypasses the air spring. The last metre is a flexible line.
Stage 6: acceptance test, proving the number
Measure floor and table surface with the same three-axis instrument, on the same day, and calculate transmissibility in 1/3 octave bands. Compare against the VC curve agreed in the specification, citing IEST-RP-CC012 for criteria, GB 50868 for design and ISO 10817 for method.
|
Criterion |
RMS velocity, 1 to 80 Hz |
Tool it suits |
What it takes to pass |
|
VC-A |
50 µm/s |
Optical microscope at 100× |
Passive on a good slab |
|
VC-B |
25 µm/s |
400× microscope, balance |
Passive with 20 percent margin |
|
VC-C |
12.5 µm/s |
1000× microscope, wire bonder |
Air or active isolation |
|
VC-D |
6.25 µm/s |
SEM, E-beam lithography |
Active or heavy-duty passive |
|
VC-E |
3.12 µm/s |
TEM, STM, interferometry |
LVH or LHV class system |
Report the octave band, not the overall value. A platform can meet 25 µm/s overall and still fail at 4 Hz, where a 1.5 Hz air spring resonates.
Where the six stages meet real projects
LeadTop runs this sequence on every platform, including a ZDT-P500 system in Wuhan with eight isolators at 1200 mm height, horizontal at or below 1.5 Hz and vertical at or below 1 Hz, carrying 28 t at 82 to 88 percent isolation at 5 Hz.
Newport, Herzan and TMC publish acceptance procedures built on the same VC criteria, so a tender written around IEST-RP-CC012 compares suppliers without favouring one. Put the standard number in the document, not a brand name.
FAQ
How long does a full installation take?
One platform on a prepared floor is normally a day for fixing and leveling, plus 24 hours of rest. Retrofits take longer, and air systems add a day for pipework.
Can the acceptance test be done without a vibrometer?
Not credibly. A phone accelerometer cannot resolve 3 µm/s at 2 Hz, and a meter without octave analysis cannot show which band fails.
What if the floor fails the baseline but there is no budget for active isolation?
Options are a heavier passive platform, moving the bench away from the disturbance, or treating the source. Measure the source first: resilient mounts on a pump often cost less than active isolation.
Does the platform need re-leveling after the building settles?
Check at 24 hours and again at one month. New slabs and fresh grout move, and 0.1 mm shows on an electronic level long before it affects an image. Annual checks suffice after that.
Are the six stages the same for rubber platforms?
Yes, with two simplifications: no air supply stage, and shims instead of a valve. Survey and acceptance stay, because rubber still has to match the spectrum.
Who signs off the acceptance?
The user's facility engineer and the installer, on one record sheet, with the octave band data attached. Without both signatures the document describes an intention.